SAP S4 HANA Migration
There have been multiple scenarios
while it comes to SAP (ECC) ERP migration to SAP S/4 HANA. SAP S4 HANA Migration It is important
to understand customers current landscape and used functionalities and modules
in the current SAP landscape/system to determine the appropriate S/4 HANA
migration scenario.
Determination of migration scenario
is so important that based on this understanding only scope, team size and
project valuation (bidding value) can be determined. For example, there could
be multiple phases (sub-projects) in one simple e.g. ECC6, EhP7 migration to
S/4 HANA 1709.
Identification of appropriate
migration scenario would help you finalizing following things:
1.
The magnitude of Work (Scope)
2.
Number of Project Phases
3.
Team Size Requirement
4.
Project Amount (Bid Amount)
Mainly this article is for the sales
team involved in approaching customers for SAP migration. I hope it helps them.
Note: This article is mainly for SAP
consultants/management who are market goers (Sales Team). Please get your
basics strong before committing anything about S/4 HANA Migration.
In this article, we would be
focusing on Scenario 6 and Scenario 7. Other Scenarios will be covered in
future articles.
Note: This document is prepared considering that first,
the migration will take place from ECC environment and required
additional functionality would be activated in the migrated S/4 HANA 1709
environment. With this, your customer would be in your hand.
SAP S/4 HANA Migration Scenarios
Note: A new scenario has been evolved in S/4 HANA 1709 for
customers who are already in SAP ERP with HANA1 (Suite on HANA) or S/4 HANA
with HANA1 (S/4 HANA Finance 1503, 1605 and S/4 HANA 1511, 1610) and want to
migrate to S/4 HANA 1709 (which is on HANA2). Migration has to be done in two
phases:
Phase1: SAP ERP o HANA (Suite on HANA) to SAP ERP HANA2 (Suite on
HANA2)
Phase2: S/4 HANA with HANA1 (S/4 HANA Finance 1503, 1605 and S/4
HANA 1511, 1610) to S/4 HANA 1709 (1709 is on HANA2)
S/4
HANA Migration Concepts (Doc. Splitting and Parallel Ledger/Accounting/HANA2)
Following points help you determining
migration scenario with respect to scenario 6 and scenario 7:
1.
There is no concept of ‘New GL or
‘Classic GL’ in S/4 HANA
2.
New GL is not a pre-perquisite for
migrating to S/4 HANA, you can migrate to S/4 HANA from classic GL
3.
Migration from Classic GL to S/4
HANA 1610 (1503, 1511, 1605 and 1610) was possible, but subsequently, document
splitting was not possible and due to this SAP recommendation was to activate
first New GL (Ledger introduction and document splitting) and then migrate to
S/4 HANA
4.
Migration from Classic GL (without
activating to New GL) to S/4 HANA 1709 is possible, additionally, now
subsequent document splitting and ledger introduction is possible in S/4 HANA
1709. This is the reason, now there is no need of doing a project for New GL
activation in ECC environment.
5.
Need to keep in mind that there
might be possible three separate projects for converting ECC on classic GL to
S/4 HANA with document splitting and parallel accounting (additional ledgers).
6.
Subsequent Ledger (Parallel Accounting)
introduction was possible from SAP S/4 HANA Finance SAP 1605 and S/4 HANA 1610.
7.
A new scenario has been evolved in
S/4 HANA 1709 for customers who are already in SAP ERP with HANA1 (Suite on
HANA) or S/4 HANA with HANA1 (S/4 HANA Finance 1503, 1605 and S/4 HANA 1511,
1610) and want to migrate to S/4 HANA 1709 (which is on HANA2). Migration has
to be done in two phases:
Project
Phases for Migrating SAP ECC System to S/4 HANA 1709
Considering there is one SAP ECC
customer with classic GLs and he wants to move to S/4 HANA 1709. He also wants
to have functionality such as document splitting and parallel accounting
(additional ledgers). SAP S4 HANA Migration.
Phase
1: ECC Migration to S/4 HANA
1.
Preparatory Phase
- System Requirement (Unicode Conversion)
- Maintenance Planner
- Pre-Checks
- Custom Code Pre-Parathion
1.
Technical Migration (SUM)
- Database Migration
- Software Upgrade
- Data Conversion
1.
Delta Customization
2.
Data (Functional) Migration
(Migration Cockpit)
3.
Testing
4.
Go-Live
Phase2: Activation of Parallel
Ledger (Non-Leading Ledger Introduction)
SAP has two approaches to meet multi
GAAP reporting requirements i.e. the accounting approach and the ledger
approach
1.
Preparatory Phase
2.
Execution Phase
3.
Post – Processing Phase
Phase3: Activation of Document
Splitting
1.
Preparatory Phase
2.
Execution Phase
3.
Post – Processing Phase
(Further detailing can be obtained
from this blog https://blogs.sap.com/2017/12/11/subsequent-document-splitting-in-s4-hana-finance-1709-on-premise/#)
Note: No SLO service is required for
activating document splitting subsequently. Standard document splitting
activation cockpit is available in IMG node in S/4 HANA 1709.
Major/Select
Changes in S/4 HANA 1709
If you are going to the customer for
sales pitch before that please get the understanding of ‘what is new in S/4
HANA 1709’.
- New HANA Data Base i.e. HANA 2 DB
- Machine Learning capabilities on S/4 HANA 1709
On-Premise
- Expanding Core with Embedded
- Innovation on Core: Demand-Driven Replacement, Advanced
Variant Configuration, Real-Time Inventory Management (e.g. Oil & Gas)
- New S/4 HANA Migration Cockpit
- A new addition to SAP Fiori Lot
- SAP S4 HANA Migration